Cost
$6.67 million
Projected completion date
August 30, 2013
The Details
The levee project is intended to protect the west side of Augusta from a flood such as the one the city endured on Halloween of 1998.
The Progress
After more than a decade of work, the project broke ground this summer. Currently, according to Corps of Engineer estimates, the project is about three percent ahead of schedule and more than $55,000 under budget.
For more information
http://www.augustagov.org/i-want-to/learn-about/corps-levee-project